How to install fertilizer production line equipment?

avatar
fertilizerproduction
How to install fertilizer production line equipment?

 The npk production line equipment usually includes: crusher, feeder, horizontal mixer, fertilizer granulator, dryer, cooler, screening machine, weighing and packaging machine. Granulators include npk fertilizer granulator, disc granulator machine, drum granulator, etc. The fertilizer granulator machine price varies.

Today mainly introduces the installation process of the npk fertilizer production line:

1. Before installation, check whether the basic dimensions of each installation meet the requirements of the drawings according to the plan and foundation drawings of the fertilizer production equipment. Inconsistencies should be repaired until each dimension is correct.

2. The installation personnel should be familiar with the installation requirements of each fertilizer production equipment, and carry out construction strictly according to the technical requirements.

3. Fertilizer production equipment may be deformed, damaged or lost during transportation. Therefore, before installation, the equipment schedule should be checked and accepted, and corresponding measures should be taken to make the equipment in good condition before installation.

4. Before entering the installation site, each fertilizer production equipment should be numbered, and the installation process card and schedule should be formulated, and transferred to the site for installation one by one according to the requirements of the installation process sequence.

5. Installation sequence: from top to bottom, first install the host equipment and rack position, and then install the connecting pipes and electrical equipment.

6. Tools required for installation: equipment and materials must be complete.

7. After the installation of each rotating part of the fertilizer production equipment, it must rotate flexibly without the sound of card collision, and each connecting part must be firmly sealed without powder leakage, air leakage, oil leakage and other phenomena.

8. The installation of electrical equipment should comply with the relevant regulations, the direction of each line should be clear, there should be no leakage, electric wires, and cables should have protective shells to prevent mice from being bitten.

9. After all the equipment is installed, each stand-alone machine should be tested with an empty vehicle, and the load test can only be carried out after the operation is normal.

10. Before the test run, calibrate the electronic batching scale and packaging scale to meet the specified accuracy.